Highway 99 Project Construction Update

Wildish Construction is scheduled to return to the site the week of November 28th. This date may change based on material and crew availability. Their focus will shift to building the retaining walls. There will be five walls on the project. Two walls will be located by the school (walls #1 and #2), one wall is located in front of the gas station (wall #3), and two walls  will be located on the corner of W E Street and W 2nd Street (walls #4 and #5). The plan is to start with Wall #1 and finish with Wall #5. You can expect this work to last until mid-January. As for traffic control, you can expect to see lane shifts and some flagging. Wildish is planning on a holiday shut down for the last two weeks in December.

For additional project information, ODOT Contact Info, or to join the ODOT Project Notification List, please visit the ODOT Project Page.

For construction related questions, please contact ODOT directly at 541-757-4211.

 

 

 