Highway 99 Project Update

The contractor continues to work on the curb between “F” and American. There was a problem with the curbs, so they were removed and repoured.

The speed reduction is put into place. It is now 25 MPH in town. This will remain until the fall.

Over the next few weeks the contractor will pour the curbs between “F” and American on both sides. Then they will prepare for sidewalks, ADA ramps, and driveways. ODOT is in  communication with property owners regarding access.

Longer term, paving between “F” and American will likely occur in May, but is highly dependent on weather.

Questions about the Project? Please Contact ODOT Public Information Officer, David House at david.j.house@odot.oregon.gov or 503-551-8641.